MGHS Frontage Improvements
Installation of Sewer, Storm and water as part of the frontage improvements for the Marysville Getchell High School Frontage Improvements.
Spotlight
Intersection Improvements – Drainage Facilities – Institutional Construction – Deep Utilities
Signalization, utility installation and roadway realignment to accommodate the main entrance of the new Getchell High School. The work was performed through the winter months and involved coordination with Snohomish PUD and other third party utility purveyors to relocate existing facilities to accommodate the new construction.
Results
The work was completed to allow the school to open one full year ahead of schedule.
Acknowledgements
Owner: Marysville School District
Contractor: New West Development Inc.
Engineer: Seiz Engineering